drag

Request a call back

Our case studies

Malrod pride ourselves on our service, and we are passionate about delivering the highest quality to our customers, no matter the nature of the job. Read through our case studies to find out more about some of the jobs that gave us such a long list of happy customers.

Projects we have worked on

Former Civic Offices, Newcastle Under Lyme

This project involved the asbestos removal of sprayed asbestos insulation to steel columns within walls, and steel beams within ceilings, throughout 3 no. adjoining blocks of offices with 4 no. floors in each block.

Additionally, we removed a number of  Asbestos Insulation Board installations within various areas of the buildings, as well as removal of asbestos insulation from within the Basement Boiler Room.

This was an 7 month project with a value of circa £900k, successfully completed on time and within budget.

Malrod Logo

circa £900k

Upper Heyford Airbase

This contract involved asbestos removal from multiple buildings on the former RAF/USAF base of circa 24 hectares. This long term project involved the co-ordination of phased demolition and asbestos removal of former administration buildings, military housing, on site hospital, military storage buildings, fuel storage tanks and vessels, on site supermarket and utility installations.

Asbestos insulation to pipework, A.I.B, sprayed asbestos insulation, asbestos cement panels, asbestos containing floor tiles, asbestos containing artex were all present in various locations throughout the numerous buildings and site confines.

Meticulously phased planning and handover of individual buildings was paramount to the successful running of this project.

Malrod logo

circa £650k

Wigan International Swimming Pool

Malrod carried out the entire asbestos removal to Wigan International Swimming Pool.

This involved the entire ceiling area of A.I.B of the main pool. The whole area had to be scaffolded to gain access and provide a suitable working platform over the pool area.

A.I.B removal was also carried out to the changing room ceilings, communal areas and corridors.

Asbestos insulation to pipework and vessels was further carried out within the Plant Room and Boiler Room areas.

Malrod logo

circa £200k

Altbridge Park, Liverpool

Large scale removal of asbestos containing Artex to Flats and Communals on a 15 storey block of flats at Liverpool.

Malrod logo

circa £120k

Bolton College

Malrod carried out large scale removal of sprayed asbestos insulation to all steelwork throughout the basement, 1st and 2nd floors of the building.

Asbestos insulation was also removed from pipework within the floor ducts on the ground floor and from pipework within the boiler room in the basement.

A.I.B wall cladding was also removed from various locations within the building.

The contract was carried out to programme (10 weeks) and at a cost circa £250k.

The building was subsequently demolished.

Bolton Council

circa £250k

The Library Wakefield

This project entailed the removal of external A.I.B window panels to all elevations. Scaffolding was erected and enclosures built utilising the scaffold structure.

A.I.B was also removed from multiple internal areas of ceilings, walls and high level window panels.

Malrod logo

circa £80k

17 Storey Block of Flats

This was a large scale project involving the removal of A.I.B (asbestos insulation board) to risers running through 17 floors in 6No. flat throughout 3No. blocks.

A.I.B removal was also carried out to ceilings within Communal Areas. Asbestos containing floor tiles were also removed prior to demolition of the blocks.

domestic

circa £400k

HMS Intrepid

Malrod carried out asbestos removal throughout the former Royal Navy vessel when in dry dock at Liverpool. Asbestos insulation was removed from pipework in numerous locations and from funnel areas and engine rooms.

A.I.B was removed from numerous cabin areas, kitchens, corridors, walls and ceilings throughout the vessel.

The vessel was de-commissioned, dismantled and scrapped following the asbestos removal contract

Navy

circa £200k